Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014
Figure 16. Removing stones from sediment basin 1, 19-10-2015.
Figure 15. Nearly a truckload of accumulated trash and garbage was collected before removal of stones and soil began. 19-10-2015.
Figure 14. The last frog standing, 21-10-2015.
Figure 64. Muaffaq Hazza, field director, and Ali Owaisi, DoA rep, discussing project strategy. 5-11-2015.
Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.