Figure 50.Ali Aqil sweeping up, 13-11-2015. Photo by Muaffaq Hazza.
Figure 18. Stone removal part 2. 19-10-2015
Figure 56. The following week some rains came. 17-11-2015. Photo by Muaffaq Hazza.
Figure 17. Sediment basin 2, stone removal, part 1. 19-10-2015
Figure 2. Butler 1913 Ill. 138. The Great Reservoir; View from the Southeast. Archaeological Archives, accessed November 25, 2015, Identifier # 925; http://vrc.princeton.edu/archives/items/show/10746.
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 43. After work, 8-11-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.