Figure 22. Stone and soil removal – experimental; it proved very difficult to flip the stones over the top edge. 22-10-2015.
Figure 25. Stone up 3. 24-10-2015.
Figure 30. Taking the high ground first – in a sea of wet sediment. 27-10-2015
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 28. While stones were being removed, another part of the team began removing the soil using buckets and ropes. The strategy was to remove the thinner layers from the edges where bedrock was higher to isolate the deeper and thicker layer in the middle. This and the following 20 photographs show the soil ‘melt’ away until the final remnant is removed from the deeper center. 20-10-2015
Figure 7. Graffiti over graffiti over the stairs, 19-10-2015
Figure 61. The north wall of Houses 87 (right) & 88 (left) exposed after the removal of the long-term reservoir cleanout mound from its south side. 10-11-2015. Photo by Muaffaq Hazza.
Figure 56. The following week some rains came. 17-11-2015. Photo by Muaffaq Hazza.