Figure 31. The rainfall was light, and the soil dried quickly. 29-10-2015
Figure 39. Contending with early rain. 7-11-2015.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014
Figure 45. Final days: Racing the clock and racing the rain. 9-11-2015
Figure 25. Stone up 3. 24-10-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 16. Removing stones from sediment basin 1, 19-10-2015.
Figure 64. Muaffaq Hazza, field director, and Ali Owaisi, DoA rep, discussing project strategy. 5-11-2015.