Figure 36. Each of two teams marked off squares for removal. 4-11-2015
Figure 47. Three days later, the last pocket of soil on the last day of scheduled team work. Photo by Muaffaq Hazza. 13-11-2015
Figure 40. Pumping the puddles; the main challenge is to keep the water away from the soil. Shown here is a small pump provided by Mayor Hassan Fahed and his municipal staff. 7-11-2015.
Figure 30. Taking the high ground first – in a sea of wet sediment. 27-10-2015
Figure 59. Onto dump small truck. 7-11-2015
Figure 35. Attacking the middle 2: four hours later, 12:02 pm, 2-11-2015.
Figure 20. Stone removal part 4; this completed the clearing of sediment basin 2, 19-10-2015.
Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.