Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 37. Arriving at the deep center. 5-11-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 60. Sediment from reservoir supplies municipal street side landscaping soil. 8-11-2015
Figure 44. After overnight showers a rain-slicked floor made the work challenging. 9-11-2015.
Figure 57. Cleaned reservoir with clean water after the first rain, 19-11-2015. Photo by Muaffaq Hazza.
Figure 9. Supply Channel, NW corner of Umm el-Jimal, 1-2-2012