Figure 31. The rainfall was light, and the soil dried quickly. 29-10-2015
Figure 16. Removing stones from sediment basin 1, 19-10-2015.
Figure 20. Stone removal part 4; this completed the clearing of sediment basin 2, 19-10-2015.
Figure 6. Water drawing station built in the 1955 preservation. The stones on the right and the left used to protrude to provide standing space for a person drawing water with a bucket on a rope. They were broken off by vandals. 3-11-2015.
Figure 26. Stone up 4. 24-10-2015.
Figure 47. Three days later, the last pocket of soil on the last day of scheduled team work. Photo by Muaffaq Hazza. 13-11-2015
Figure 23 Stone up 1. 24-10-2015.
Figure 63. Contribution of the Municipality. Mayor Hassan Fahed (right) and Muaffaq Hazza. 7-11-2015