Figure 56. The following week some rains came. 17-11-2015. Photo by Muaffaq Hazza.
Figure 51. Detol Chlorine and Dish Soap for the power wash solution. 14-11-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 8. Wadi Za’atari in Umm el-Jimal, 1-2-2012.
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 44. After overnight showers a rain-slicked floor made the work challenging. 9-11-2015.