Figure 11. Reservoir with residue of rain-supplied water from the winter of 2014-5, 19-9-2015.
Figure 45. Final days: Racing the clock and racing the rain. 9-11-2015
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 52. Mayor Hasan Fahed Rgaibeh starting power wash. 14-11-2015.
Figure 6. Water drawing station built in the 1955 preservation. The stones on the right and the left used to protrude to provide standing space for a person drawing water with a bucket on a rope. They were broken off by vandals. 3-11-2015.
Figure 51. Detol Chlorine and Dish Soap for the power wash solution. 14-11-2015.
Figure 36. Each of two teams marked off squares for removal. 4-11-2015
Figure 46. Left to be done in in the last 4 days, 10-13 November. 9-11-2015.