Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.
Figure 64. Payday in the rain shelter of the House XIII great room. Ali Aqil and Bert de Vries distributing the weekly payroll, 5-11-2015. Photo by Muaffaq Hazza
Figure 57. Cleaned reservoir with clean water after the first rain, 19-11-2015. Photo by Muaffaq Hazza.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 16. Removing stones from sediment basin 1, 19-10-2015.
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.