Figure 9. Supply Channel, NW corner of Umm el-Jimal, 1-2-2012
Figure 18. Stone removal part 2. 19-10-2015
Figure 64. Muaffaq Hazza, field director, and Ali Owaisi, DoA rep, discussing project strategy. 5-11-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 20. Stone removal part 4; this completed the clearing of sediment basin 2, 19-10-2015.
Figure 57. Cleaned reservoir with clean water after the first rain, 19-11-2015. Photo by Muaffaq Hazza.
Figure 52. Mayor Hasan Fahed Rgaibeh starting power wash. 14-11-2015.
Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.