Figure 36. Each of two teams marked off squares for removal. 4-11-2015
Figure 9. Supply Channel, NW corner of Umm el-Jimal, 1-2-2012
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 24. Stone up 2. 24-10-2015.
Figure 17. Sediment basin 2, stone removal, part 1. 19-10-2015
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 58. Removing sediment mound from this and earlier cleanouts south side of reservoir. 7-11-2015.
Figure 61. The north wall of Houses 87 (right) & 88 (left) exposed after the removal of the long-term reservoir cleanout mound from its south side. 10-11-2015. Photo by Muaffaq Hazza.