Figure 38. Stratified sediment, 50 cm deep. 5-11-2015.
Figure 57. Cleaned reservoir with clean water after the first rain, 19-11-2015. Photo by Muaffaq Hazza.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.
Figure 61. The north wall of Houses 87 (right) & 88 (left) exposed after the removal of the long-term reservoir cleanout mound from its south side. 10-11-2015. Photo by Muaffaq Hazza.
Figure 63. Contribution of the Municipality. Mayor Hassan Fahed (right) and Muaffaq Hazza. 7-11-2015
Figure 14. The last frog standing, 21-10-2015.
Figure 45. Final days: Racing the clock and racing the rain. 9-11-2015