Figure 11. Reservoir R19 with soil heaps; looking to southwest. 11 Oct 2016.
Figure 5. The energetic crew that completed the R7 excavation. 20 Oct 2017.
Figure 17. Close up view of quarry marks. Below the 10-cm scale stick the groove in which wood wedges soaked with water were jammed is clearly visible. Because of the fine-grained igneous texture, the basalt blocks split of smoothly, similar to a flint sliver knapped from a core. 1 November, 2016.
Figure 16. Reservoir R19 at end of season; final cleanup to be done in 2017. 2 November 2016.
Figure 23. The cleaned portion of exposed floor. Proper care of this water source will require periodic cleaning of the entire reservoir floor, at times when the entire water supply is used up. 27 October, 2016.
Figure 18. The undisturbed sediment area in Reservoir R16. 29 October, 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.