Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 7. Reservoir R31 just after the cleanout began, 11 Oct. 2016.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 15. In the final week, a new crew began the clearing of stones from the Reservoir R19 itself. 1 Nov. 2016.
Figure 21. The dry south west corner of Reservoir 13 with its deposit of plastic bottles on top of algae ‘rooted’ in about 3 cm of new sediment. 26 October, 2016.
Figure 3. Excavation of the rubble approaching completion. 25 October 2016.
Figure 25. Team 2. The Group mostly responsible for clearing the deep stone layer from Quarry-Reservoir R19. 2 November, 2016.
Figure 17. Close up view of quarry marks. Below the 10-cm scale stick the groove in which wood wedges soaked with water were jammed is clearly visible. Because of the fine-grained igneous texture, the basalt blocks split of smoothly, similar to a flint sliver knapped from a core. 1 November, 2016.