Figure 4. Reservoir R7 cleaning completed. The Druze-constructed pillars supported the roof. 1 Nov. 2016
Figure 5. The energetic crew that completed the R7 excavation. 20 Oct 2017.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 12. Reservoir with rock and soil heaps; looking north. 11 Oct. 2016.
Figure 21. The dry south west corner of Reservoir 13 with its deposit of plastic bottles on top of algae ‘rooted’ in about 3 cm of new sediment. 26 October, 2016.
Figure 11. Reservoir R19 with soil heaps; looking to southwest. 11 Oct 2016.
Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.