Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 7. Reservoir R31 just after the cleanout began, 11 Oct. 2016.
Figure 2. Reservoir R7 in courtyard of House 52 before work began. 10 Oct 2016.
Figure 15. In the final week, a new crew began the clearing of stones from the Reservoir R19 itself. 1 Nov. 2016.
Figure 20. Reservoir 13 with water remaining to an average depth of one meter. In the foreground one can see the shelf of exposed bedrock floor and the algae bloom in the shallower water. 26 October 2016.
Figure 9. Reservoir R7 after cleanout, with 20th century plaster intact. 27 October 2016.
Figure 13. Removal of twentieth century reservoir cleanout. 12 Oct. 2016.
Figure 18. The undisturbed sediment area in Reservoir R16. 29 October, 2016.