Figure 2. Reservoir R7 in courtyard of House 52 before work began. 10 Oct 2016.
Figure 23. The cleaned portion of exposed floor. Proper care of this water source will require periodic cleaning of the entire reservoir floor, at times when the entire water supply is used up. 27 October, 2016.
Figure 25. Team 2. The Group mostly responsible for clearing the deep stone layer from Quarry-Reservoir R19. 2 November, 2016.
Figure 5. The energetic crew that completed the R7 excavation. 20 Oct 2017.
Figure 15. In the final week, a new crew began the clearing of stones from the Reservoir R19 itself. 1 Nov. 2016.
Figure 17. Close up view of quarry marks. Below the 10-cm scale stick the groove in which wood wedges soaked with water were jammed is clearly visible. Because of the fine-grained igneous texture, the basalt blocks split of smoothly, similar to a flint sliver knapped from a core. 1 November, 2016.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 22. Crew members begin cleaning of sediment and algae. 26 October, 2016