Figure 48. The last bit of sediment disappearing, 10 am, 13-11-2015. The team had chosen to work Friday instead of Saturday, to have their Grand Finale a day early! Photo by Muaffaq Hazza.
Figure 58. Removing sediment mound from this and earlier cleanouts south side of reservoir. 7-11-2015.
Figure 37. Arriving at the deep center. 5-11-2015.
Figure 39. Contending with early rain. 7-11-2015.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014
Figure 12. A huge quantity of stone was thrown into the reservoir in the past 20 years. Foreman Ali Aqil serves as scale, 19-9-2015.
Figure 61. The north wall of Houses 87 (right) & 88 (left) exposed after the removal of the long-term reservoir cleanout mound from its south side. 10-11-2015. Photo by Muaffaq Hazza.