Figure 11. Reservoir R19 with soil heaps; looking to southwest. 11 Oct 2016.
Figure 22. Crew members begin cleaning of sediment and algae. 26 October, 2016
Figure 1. Map of reservoirs in the middle of Byzantine Umm el-Jimal.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.
Figure 20. Reservoir 13 with water remaining to an average depth of one meter. In the foreground one can see the shelf of exposed bedrock floor and the algae bloom in the shallower water. 26 October 2016.
Fig. 6. Supply channel created by the Masa’eid to direct the overflow from R13 to Reservoir R7. 2 Nov. 2016.
Figure 23. The cleaned portion of exposed floor. Proper care of this water source will require periodic cleaning of the entire reservoir floor, at times when the entire water supply is used up. 27 October, 2016.