Figure 22. Crew members begin cleaning of sediment and algae. 26 October, 2016
Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.
Figure 3. Excavation of the rubble approaching completion. 25 October 2016.
Figure 18. The undisturbed sediment area in Reservoir R16. 29 October, 2016.
Figure 20. Reservoir 13 with water remaining to an average depth of one meter. In the foreground one can see the shelf of exposed bedrock floor and the algae bloom in the shallower water. 26 October 2016.
Figure 10. Twentieth Century surface supply channel collected runoff from open field to north of Reservoir R31. Oct 10, 2016.
Figure 12. Reservoir with rock and soil heaps; looking north. 11 Oct. 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.