Figure 18. The undisturbed sediment area in Reservoir R16. 29 October, 2016.
Figure 3. Excavation of the rubble approaching completion. 25 October 2016.
Figure 21. The dry south west corner of Reservoir 13 with its deposit of plastic bottles on top of algae ‘rooted’ in about 3 cm of new sediment. 26 October, 2016.
Figure 2. Reservoir R7 in courtyard of House 52 before work began. 10 Oct 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 13. Removal of twentieth century reservoir cleanout. 12 Oct. 2016.
Figure 5. The energetic crew that completed the R7 excavation. 20 Oct 2017.