Figure 7. Reservoir R31 just after the cleanout began, 11 Oct. 2016.
Figure 12. Reservoir with rock and soil heaps; looking north. 11 Oct. 2016.
Fig. 6. Supply channel created by the Masa’eid to direct the overflow from R13 to Reservoir R7. 2 Nov. 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 20. Reservoir 13 with water remaining to an average depth of one meter. In the foreground one can see the shelf of exposed bedrock floor and the algae bloom in the shallower water. 26 October 2016.
Figure 16. Reservoir R19 at end of season; final cleanup to be done in 2017. 2 November 2016.
Figure 15. In the final week, a new crew began the clearing of stones from the Reservoir R19 itself. 1 Nov. 2016.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.