Figure 2. Butler 1913 Ill. 138. The Great Reservoir; View from the Southeast. Archaeological Archives, accessed November 25, 2015, Identifier # 925; http://vrc.princeton.edu/archives/items/show/10746.
Figure 41. Another way was to dam up the puddles and move the water away sideways. 8-11-2015.
Figure 20. Stone removal part 4; this completed the clearing of sediment basin 2, 19-10-2015.
Figure 22. Stone and soil removal – experimental; it proved very difficult to flip the stones over the top edge. 22-10-2015.
Figure 46. Left to be done in in the last 4 days, 10-13 November. 9-11-2015.
Figure 51. Detol Chlorine and Dish Soap for the power wash solution. 14-11-2015.
Figure 37. Arriving at the deep center. 5-11-2015.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.