Figure 45. Final days: Racing the clock and racing the rain. 9-11-2015
Figure 32. NE corner 1. 1-11-2015
Figure 39. Contending with early rain. 7-11-2015.
Figure 19. Stone removal part 3. 19-10-2015
Figure 25. Stone up 3. 24-10-2015.
Figure 20. Stone removal part 4; this completed the clearing of sediment basin 2, 19-10-2015.
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014