Figure 9. Supply Channel, NW corner of Umm el-Jimal, 1-2-2012
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 33. NE corner 2. Full buckets ‘flew’ up rapidly, and mounds of soil accumulated. 1-11-2015.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014
Figure 22. Stone and soil removal – experimental; it proved very difficult to flip the stones over the top edge. 22-10-2015.
Figure 28. While stones were being removed, another part of the team began removing the soil using buckets and ropes. The strategy was to remove the thinner layers from the edges where bedrock was higher to isolate the deeper and thicker layer in the middle. This and the following 20 photographs show the soil ‘melt’ away until the final remnant is removed from the deeper center. 20-10-2015