Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 40. Pumping the puddles; the main challenge is to keep the water away from the soil. Shown here is a small pump provided by Mayor Hassan Fahed and his municipal staff. 7-11-2015.
Figure 37. Arriving at the deep center. 5-11-2015.
Figure 32. NE corner 1. 1-11-2015
Figure 10. Roman Reservoir the day after the rains, 2-2-2012.
Figure 28. While stones were being removed, another part of the team began removing the soil using buckets and ropes. The strategy was to remove the thinner layers from the edges where bedrock was higher to isolate the deeper and thicker layer in the middle. This and the following 20 photographs show the soil ‘melt’ away until the final remnant is removed from the deeper center. 20-10-2015