Figure 38. Stratified sediment, 50 cm deep. 5-11-2015.
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 15. Nearly a truckload of accumulated trash and garbage was collected before removal of stones and soil began. 19-10-2015.
Figure 43. After work, 8-11-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 26. Stone up 4. 24-10-2015.
Figure 8. Wadi Za’atari in Umm el-Jimal, 1-2-2012.
Figure 29. Soil removal – bucket by bucket, after the first rain, 26-10-2014