Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.
Figure 17. Close up view of quarry marks. Below the 10-cm scale stick the groove in which wood wedges soaked with water were jammed is clearly visible. Because of the fine-grained igneous texture, the basalt blocks split of smoothly, similar to a flint sliver knapped from a core. 1 November, 2016.
Figure 18. The undisturbed sediment area in Reservoir R16. 29 October, 2016.
Figure 3. Excavation of the rubble approaching completion. 25 October 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Fig. 6. Supply channel created by the Masa’eid to direct the overflow from R13 to Reservoir R7. 2 Nov. 2016.
Figure 19. Refilling the bulldozer gauges on the west edge of Reservoir R16. 29 October, 2016.
Figure 11. Reservoir R19 with soil heaps; looking to southwest. 11 Oct 2016.