Figure 25. Team 2. The Group mostly responsible for clearing the deep stone layer from Quarry-Reservoir R19. 2 November, 2016.
Figure 2. Reservoir R7 in courtyard of House 52 before work began. 10 Oct 2016.
Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.
Figure 23. The cleaned portion of exposed floor. Proper care of this water source will require periodic cleaning of the entire reservoir floor, at times when the entire water supply is used up. 27 October, 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 16. Reservoir R19 at end of season; final cleanup to be done in 2017. 2 November 2016.
Figure 9. Reservoir R7 after cleanout, with 20th century plaster intact. 27 October 2016.
Figure 12. Reservoir with rock and soil heaps; looking north. 11 Oct. 2016.