Figure 11. Reservoir R19 with soil heaps; looking to southwest. 11 Oct 2016.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 9. Reservoir R7 after cleanout, with 20th century plaster intact. 27 October 2016.
Figure 21. The dry south west corner of Reservoir 13 with its deposit of plastic bottles on top of algae ‘rooted’ in about 3 cm of new sediment. 26 October, 2016.
Figure 22. Crew members begin cleaning of sediment and algae. 26 October, 2016
Figure 13. Removal of twentieth century reservoir cleanout. 12 Oct. 2016.
Figure 20. Reservoir 13 with water remaining to an average depth of one meter. In the foreground one can see the shelf of exposed bedrock floor and the algae bloom in the shallower water. 26 October 2016.