Figure 8. Crew removing building blocks from Reservoir R31. 20 October 2016.
Figure 20. Reservoir 13 with water remaining to an average depth of one meter. In the foreground one can see the shelf of exposed bedrock floor and the algae bloom in the shallower water. 26 October 2016.
Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 15. In the final week, a new crew began the clearing of stones from the Reservoir R19 itself. 1 Nov. 2016.
Figure 13. Removal of twentieth century reservoir cleanout. 12 Oct. 2016.
Figure 21. The dry south west corner of Reservoir 13 with its deposit of plastic bottles on top of algae ‘rooted’ in about 3 cm of new sediment. 26 October, 2016.
Fig. 6. Supply channel created by the Masa’eid to direct the overflow from R13 to Reservoir R7. 2 Nov. 2016.
Figure 16. Reservoir R19 at end of season; final cleanup to be done in 2017. 2 November 2016.