Figure 19. Refilling the bulldozer gauges on the west edge of Reservoir R16. 29 October, 2016.
Figure 18. The undisturbed sediment area in Reservoir R16. 29 October, 2016.
Fig. 6. Supply channel created by the Masa’eid to direct the overflow from R13 to Reservoir R7. 2 Nov. 2016.
Figure 7. Reservoir R31 just after the cleanout began, 11 Oct. 2016.
Figure 23. The cleaned portion of exposed floor. Proper care of this water source will require periodic cleaning of the entire reservoir floor, at times when the entire water supply is used up. 27 October, 2016.
Figure 24. Team 1. The group that worked the first two weeks and is mostly responsible for the clearing and cleaning of reservoirs R7 and R31.
Figure 5. The energetic crew that completed the R7 excavation. 20 Oct 2017.
Figure 2. Reservoir R7 in courtyard of House 52 before work began. 10 Oct 2016.