Figure 14. Leveled area looking south-southwest across Reservoir R19. 25 October 2016.
Figure 21. The dry south west corner of Reservoir 13 with its deposit of plastic bottles on top of algae ‘rooted’ in about 3 cm of new sediment. 26 October, 2016.
Figure 11. Reservoir R19 with soil heaps; looking to southwest. 11 Oct 2016.
Figure 2. Reservoir R7 in courtyard of House 52 before work began. 10 Oct 2016.
Figure 10. Twentieth Century surface supply channel collected runoff from open field to north of Reservoir R31. Oct 10, 2016.
Figure 12. Reservoir with rock and soil heaps; looking north. 11 Oct. 2016.
Figure 16. Reservoir R19 at end of season; final cleanup to be done in 2017. 2 November 2016.
Figure 4. Reservoir R7 cleaning completed. The Druze-constructed pillars supported the roof. 1 Nov. 2016