Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.
Figure 39. Contending with early rain. 7-11-2015.
Figure 62. The crew. Ali Aqil, standing far right, was the group’s foreman whose work strategy enabled the completion of the reservoir reconditioning in four weeks. Photo by visitor, 7-11-2015.
Figure 57. Cleaned reservoir with clean water after the first rain, 19-11-2015. Photo by Muaffaq Hazza.
Figure 6. Water drawing station built in the 1955 preservation. The stones on the right and the left used to protrude to provide standing space for a person drawing water with a bucket on a rope. They were broken off by vandals. 3-11-2015.
Figure 48. The last bit of sediment disappearing, 10 am, 13-11-2015. The team had chosen to work Friday instead of Saturday, to have their Grand Finale a day early! Photo by Muaffaq Hazza.
Figure 18. Stone removal part 2. 19-10-2015
Figure 61. The north wall of Houses 87 (right) & 88 (left) exposed after the removal of the long-term reservoir cleanout mound from its south side. 10-11-2015. Photo by Muaffaq Hazza.