Figure 56. The following week some rains came. 17-11-2015. Photo by Muaffaq Hazza.
Figure 5. Dedication of USAID funded re-plastering of the reservoir: “Inception of the repair of this reservoir was on 22 December 1954; and completion was on 28 February, 1955. The writer of the line of text was Rakan Ibn Awdah es-Serour.” 10-21-2015.
Figure 57. Cleaned reservoir with clean water after the first rain, 19-11-2015. Photo by Muaffaq Hazza.
Figure 38. Stratified sediment, 50 cm deep. 5-11-2015.
Figure 12. A huge quantity of stone was thrown into the reservoir in the past 20 years. Foreman Ali Aqil serves as scale, 19-9-2015.
Figure 4. 3 November, 2015, 110 years later, and 60 years after re plastering of the masonry and bedrock. The bosses of the draughted masonry remain visible as bumps in the thick layer of cement, but the “coping” has been removed. 3-11-2015.
Figure 16. Removing stones from sediment basin 1, 19-10-2015.
Figure 36. Each of two teams marked off squares for removal. 4-11-2015